Project; Brewery Crescent, Redruth (Penventon) Location; Redruth, Cornwall Client; Little Vauxhall Contract; £5.7m Duration; circa 46 weeks. Project Description; Consisting of 51 new dwellings, Brewery Close is a collection of timberframe purpose built homes for...
Aug 13, 2020 | Case Studies, Housing
Project; Seaton Beach (PassivHaus Plus Apartments) Location; Seaton, Devon Client; Seaton Beach Developments Contract; £2.4m Duration; circa 60 weeks. Project Description; Seaton Beach Apartments is the very first multi block PassivHaus Plus apartments in the United...
Jan 31, 2019 | Case Studies, Domestic, Housing
Project; Fairway Gardens Location; Sparkwell, Devon Client; Blue Cedar Homes Contract; £3.5m Duration; 55 weeks. Project Description; Situated less than two miles from the edge of picturesque Dartmoor; Fairway Gardens is a collection of 23 beautiful new-build...
Jan 31, 2019 | Case Studies, Domestic, Housing
Project; Private Residential Location; North Cornwall Client; Private Client Contract; circa £500K Duration; 52 weeks. Project Description; Nestled into the bank of a north Cornwall creek, the property enjoys a commanding yet secluded location and incorporates a...
Nov 20, 2018 | Case Studies, Housing
Project; The RowansLocation; Sackville Close, PlymstockClient; Aster HomesContract; circa £3.5mDuration; 55 weeks. Project Description; The Rowans at Sackville Close is a collection of beautifully presented new-build properties. The development of 28 dwellings was...
Oct 16, 2018 | Case Studies, Domestic, Housing
Project; Tankersely Location; Tavistock Contract; circa £450k Duration; 26 weeks. Project Description; Classic Builders was appointed to build Tankersley; a remarkable new dwelling located within secluded private grounds in Tavistock. Set over two floors, the detached...
Jun 12, 2018 | Case Studies, Housing, Refurbishment
Project; Former Ship Hostel. Location; George Place, Stonehouse, Plymouth, Devon. Client; QSH construction PLC. Contract; circa £1m. Duration; 46 weeks. Project Description; The project consisted of the refurbishment and alterations of the Former Ship Hostel –...
Dec 2, 2014 | Case Studies, Housing
Project; Salcombe Court. Location; Cliff Road, Salcombe, Devon. Client; Owner. Contract; Circa £1.5m. Duration; 18 months. Project Description; Salcombe Court is a magnificent period house which was unfortunately fire damaged. Classic Builders were on site for 18...