Project; Hotel Chocolat
Location; Truro City Centre
Client; Salterns Investments Limited
Contract; circa £350K
Duration; 8 weeks.
Project Description;
Classic Builders has completed major refurbishment works to assist in bringing Hotel Chocolat to Truro city centre.
The former retail space (dating back to the 1700s) was in desperate need of modernisation and underwent an extensive transformation by Classic Builders. Works included a total refurbishment of the building over three floors, major structural works, complete re-roofing, all new hardwood external glazing (in accordance with local heritage and conservation guidelines), all new M&E package, new shop front and extensive fit out.
Significant challenges included limited access along one of Truro’s busiest one-way city centre roads, night time working (to meet the client’s completion date) and the addition of all new welfare facilities within the existing building.
The project was completed to the client’s expectations and Classic Builders is particularly proud as the retail space was opened in time for Christmas Shoppers to enjoy.